Traffic system improvements are coming to the northwest Las Vegas valley, with construction anticipated in the area over the next nine months.
Lane restrictions are expected on Dec. 14 at the Farm Road and Oso Blanca Road intersection in preparation for a new traffic signal, one of seven being added to the area.
Other road improvements include one pedestrian flasher beacon, roadway surface, curb and gutters, sidewalk, ADA access and fiber-optic cable installation for Intelligent Transportation Systems (ITS). Travel lanes will be reduced intermittently to facilitate the planned construction of these improvements.
# |
WORK AREA |
ANTICIPATED START |
ANTICIPATED DURATION |
1 |
Farm Rd and Oso Blanca Rd |
December |
90 calendar days |
2 |
Oso Blanca Rd and Grand Montecito Pkwy |
March |
70 calendar days |
3 |
Grand Teton Dr and Hualapai Way |
March |
70 calendar days |
4 |
Grand Teton Dr and Grand Canyon Dr |
April |
60 calendar days |
5 |
Farm Rd and Grand Canyon Dr |
June |
70 calendar days |
6 |
Deer Springs Way and Grand Canyon Dr |
July |
80 calendar days |
7 |
Centennial Pkwy and Fort Apache Rd |
July |
60 calendar days |
Courtesy: City of Las Vega
Crews will work between the hours of 7 a.m. and 3:30 p.m., Monday through Friday, for approximately nine months. No night work is planned in residential areas at this time, but that may change. Click HERE for specific areas of upcoming construction.
The project has a budget of $3.7 million, with funding provided by the Regional Transportation Commission of Southern Nevada Fuel Revenue Indexing tax and city of Las Vegas Traffic Impact Fees.
Follow us on:
FB: Ken Couture Realty Your Home Sold Guaranteed
IG: @kencouturerealtylv
Twitter: Ken Couture
Pinterest: Ken Couture
LinkedIn: Ken Couture Your Home Sold Guaranteed
Contact us at:
Ken@CoutureRealtyLV.com
(702) 476-0060